Data centers and new power in Jackson County, AR

1.2 GW of new power is waiting to connect to the grid in Jackson County, AR — 4 active requests. Typical wait: 4.1 years. 6 projects are built, 11 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Jackson County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Jackson County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Jackson County right now.

1.2 GW
of new power is waiting to connect
4 projects asked. Not yet approved. Roughly what 960,000 homes use.
2.1 GW
has actually been built
6 projects switched on so far.
4.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 29%
  • Still waiting 19%
  • Withdrawn 52%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Jackson County.

What kind of power is asking to connect

  • Wind 42%
  • Solar 42%
  • Solar + battery 17%

By capacity requested. Data as of 14 October 2026.

All the numbers

21 requests ever filed
Pending applications
4
of 21 ever filed
Capacity queued
1.2 GW
requested, not committed
Already built
2.1 GW
6 projects connected
Built vs decided
35.3%
11 withdrawn
Median wait
4.1 yr
for applications still pending
Connected capacity
184 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built62.1 GW28.6%
Still waiting41.2 GW19.0%
Withdrawn112.6 GW52.4%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Wind2500 MW
Solar1500 MW
Solar + battery1200 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
INDEPENDENCE-ISES - POWERLINE ROAD 500.0kVSolar625 MWcompleted2021-10MISO
INDEPENDENCE-ISES - POWERLINE ROAD 500.0kVSolar625 MWcompleted2021-10MISO
MALLORY 161Solar500 MWcompleted2021-11MISO
Independence (A)(500kV) to Powerline (B) (500 kV)Solar500 MWwithdrawn2022-09MISO
Mallory 161 kV SubstationSolar500 MWactive2022-09MISO
Independence-ISES- Newport 161 KVSolar500 MWwithdrawn2022-09MISO
Cash - Newport ABSolar300 MWwithdrawn2022-07MISO
HOLLAND BOTTOM - INDEPENDENCE-ISES 500.0kVWind300 MWactive2022-09MISO
Newport Ab-Cash 161kVSolar250 MWwithdrawn2022-09MISO
Swifton to Hoxie 161 kVSolar220 MWwithdrawn2022-09MISO
PECAN ST - AECC BALCH 161.0kVSolar200 MWwithdrawn2024-05MISO
INDEPENDENCE-ISES - POWERLINE ROAD 500 kVSolar200 MWwithdrawn2022-09MISO
Taping 'Newport AB / NEWPORTSOLAR (338177)' to 'Cash / 5CASH (338171)' 161kV LinSolar + battery200 MWactive2022-09MISO
NEWPORTWind200 MWactive2022-09MISO
Cash - Newport AB 161 kV Line TapSolar180 MWcompleted2017-06MISO

How Jackson County compares

#319 in the US · #4 in AR

Jackson County ranks #319 of 1,607 US counties by power waiting to connect, and #4 of 34 in Arkansas.

Common questions about power in Jackson County

How long does it take to get power for a data center in Jackson County, AR?

The median wait for a project still in the interconnection queue in Jackson County is 4.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 6 projects in Jackson County have reached energization and 11 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Jackson County, AR?

1.2 GW is currently requested across 4 active interconnection requests, and 2.1 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Jackson County, AR a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Arkansas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Jackson County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Jackson County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Jackson County on the map County reports All of Arkansas