Data centers and new power in Lee County, AL
351 MW of new power is waiting to connect to the grid in Lee County, AL — 2 active requests. Typical wait: 1.5 years. 1 projects are built, 11 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Lee County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Lee County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Lee County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Lee County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
16 requests ever filed
Source: interconnection queues published by SOCO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 1 | 620 MW | 6.2% |
| Still waiting | 2 | 351 MW | 12.5% |
| Withdrawn | 11 | 6.0 GW | 68.8% |
| Paused | 2 | — | 12.5% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Natural gas | 2 | 351 MW |
Key dates for projects here
no dated windows published
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 15 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| IC-252 | Natural gas | 968 MW | withdrawn | 2011-02 | SOCO |
| IC-224 | Natural gas | 667 MW | withdrawn | 2007-11 | SOCO |
| IC-203 | Natural gas | 655 MW | withdrawn | 2003-09 | SOCO |
| IC-1218 | Natural gas | 640 MW | withdrawn | 2023-12 | SOCO |
| IC-104 | Natural gas | 630 MW | withdrawn | — | SOCO |
| IC-210 | Natural gas | 630 MW | withdrawn | 2003-09 | SOCO |
| Franklin 3 (Goat Rock 3) | Natural gas | 620 MW | completed | — | SOCO |
| Franklin 2 (Goat Rock 2) | Natural gas | 620 MW | completed | — | SOCO |
| IC-065 | Natural gas | 610 MW | withdrawn | — | SOCO |
| IC-202 | Natural gas | 595 MW | withdrawn | 2003-09 | SOCO |
| Franklin 1 (Goat Rock 1) | Natural gas | 590 MW | completed | — | SOCO |
| IC-251 | Natural gas | 520 MW | withdrawn | 2011-02 | SOCO |
| 25-IC-1320A | Natural gas | 240 MW | active | 2025-04 | SOCO |
| IC-1251 | Solar | 157 MW | suspended | 2024-03 | SOCO |
| 25-IC-1321 | Natural gas | 111 MW | active | 2025-04 | SOCO |
How Lee County compares
#730 in the US · #12 in AL
Lee County ranks #730 of 1,607 US counties by power waiting to connect, and #12 of 35 in Alabama.
| County | Waiting | Capacity queued |
|---|---|---|
| Mobile County | 4 | 1.2 GW |
| Colbert County | 2 | 958 MW |
| Perry County | 4 | 656 MW |
| Morgan County | 1 | 528 MW |
| Autauga County | 4 | 478 MW |
| Limestone County | 4 | 471 MW |
| Baldwin County | 3 | 459 MW |
| Jackson County | 2 | 399 MW |
Common questions about power in Lee County
How long does it take to get power for a data center in Lee County, AL?
The median wait for a project still in the interconnection queue in Lee County is 1.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Lee County have reached energization and 11 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Lee County, AL?
351 MW is currently requested across 2 active interconnection requests, and 620 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Lee County, AL a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Alabama policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Lee County — SOCO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on Lee County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.